Taiwan introduces bidding framework for storage deployment at existing PV plants

What happened
Based on PV Magazine · Nov 18, 2026

Taiwan’s Ministry of Economic Affairs launched a bidding framework on November 6, 2024, to integrate battery storage with existing solar PV plants over 1 MW, aiming to enhance grid stability and renewable energy flexibility.

Taiwan introduces bidding framework for storage deployment at existing PV plants
PV Magazine — pv magazine
Key points
·
Taiwan’s MOEA introduced a bidding framework on November 6, 2024, for storage at existing solar PV plants over 1 MW.
·
Eligible projects must install at least 2.61 MWh of storage per MW of rated power and complete installation within 15 months.
·
Approved projects must release grid capacity equal to 1.5 times the rated storage power to improve infrastructure utilization.
Key numbers
·
The initiative targets grid-connected facilities exceeding 1 MW, requiring storage capacity of at least 2.
·
61 MWh per MW of rated power.
·
Projects must complete installation and grid connection within 15 months of approval.

Taiwan’s Ministry of Economic Affairs (MOEA) introduced a regulatory framework on November 6, 2024, to encourage battery energy storage systems (BESS) at existing solar PV plants. The initiative targets grid-connected facilities exceeding 1 MW, requiring storage capacity of at least 2.61 MWh per MW of rated power. Successful applicants will be selected through competitive bidding, with tariffs determined by market-based pricing. Projects must complete installation and grid connection within 15 months of approval.

The framework mandates that approved projects release grid connection capacity equal to 1.5 times the rated storage power, subject to conditions. This provision aims to improve utilization of Taiwan’s grid infrastructure and enable further renewable energy integration. A daily guaranteed billing quantity of 2.61 times the rated storage power capacity is also required, with discharge coordinated by Taipower’s scheduling and dispatch rules.

The new rules are part of Taiwan’s broader push to expand renewable energy while addressing grid stability challenges. The MOEA announced plans in January 2025 to accelerate solar and offshore wind deployment, targeting an additional 8.2 GW by the end of 2026. However, progress has lagged, with GlobalData forecasting cumulative solar capacity to reach 31.2 GW by 2035, now expected in 2029.

Energy storage is gaining traction in Taiwan, with French manufacturer Saft planning to supply 356 MWh for a Taichung project by 2026, adding to its island-wide capacity of 630 MWh. Earlier examples include a 15 MW/15 MWh battery system paired with a 150 MW solar park in southern Taiwan, highlighting growing storage integration with solar generation.